From: jon <jon@(email surpressed)> Subject: adding individual frames Date: Thu, 05 Oct 2006 13:43:36 -0400 |
Msg# 1400 View Complete Thread (2 articles) | All Threads Last Next |
I had a render which failed on certain frames. If the job was submitted
with a batch of 5, is it possible to add single frames to the queue?
When I use the add in Irush, it adds a batch of 5 starting with the
frame I specified, for example, entering 47 gives me a batch of frames
47-51, not just the frame I want.
thanks Jon |
From: Greg Ercolano <erco@(email surpressed)> Subject: Re: adding individual frames Date: Thu, 05 Oct 2006 15:44:27 -0400 |
Msg# 1401 View Complete Thread (2 articles) | All Threads Last Next |
jon wrote: [posted to rush.general]I had a render which failed on certain frames. If the job was submitted with a batch of 5, is it possible to add single frames to the queue? When I use the add in Irush, it adds a batch of 5 starting with the frame I specified, for example, entering 47 gives me a batch of frames 47-51, not just the frame I want. When you have a batched job, all frames in that job will be batched regardless. The only way to do single fix frames in a batch job is to either: > Using 'Job Edit', go into the "Command:" window, find the batching value (in your case, '5') and change it to '1'. From then on, the job will render single frames when you add frames (or even requeue existing ones) - or - > Submit a /separate/ job with a batching value of '1' to render those single fix frames -- Greg Ercolano, erco@(email surpressed) Rush Render Queue, http://seriss.com/rush/ Tel: (Tel# suppressed) Fax: (Tel# suppressed) Cel: (Tel# suppressed) |